Barcelona Padel Center (Barcelona, Spain, 2025)
Project scale: 4 courts, 600m² total
Challenge
Urban installation with limited access. Need to minimize on-site labor and disruption to surrounding businesses.
Solution
Pre-assembled modular panels delivered in sequence. Night-time installation during low-traffic hours. Project completed 1 week ahead of schedule.
Results
- 4 courts operational in 3 weeks (vs typical 6 weeks)
- Zero complaints from neighboring businesses
- Client opened for season launch as planned
- 30% labor cost savings vs traditional installation